Al Ghadeer Centre – Bilal, Tanga - Project Progress Update

Alhamdulillah, the construction of Al Ghadeer Centre – Bilal Tanga officially commenced on 15th January 2026. Since inception, the project has maintained steady progress in line with the planned schedule, supported by coordinated efforts between the AFED/Bilal, consultants, and site team.



To date, substructure works have been fully completed, including site clearance, excavation, foundation casting, and ground floor slab works. The structure has now transitioned into the superstructure phase, with works currently progressing toward the first-floor slab level. Reinforcement, formwork, and concrete activities are ongoing, with strict adherence to structural drawings and engineering specifications. 


The project involves the development of an 8-storey multi-functional building, designed to serve both educational and residential purposes. The facility will include: 


  • Dedicated Hawza classrooms to support religious education

  • Administrative offices to manage institutional operations

  • A boys’ hostel to accommodate students in a structured environment

  • Teachers’ residential apartments to ensure proximity and convenience for staff


This integrated design aims to create a self-sustaining academic environment that supports both learning and living within a single development.



On 14th April 2026, the second site meeting was successfully conducted, bringing together key stakeholders to review progress and address technical and operational matters. The meeting covered important aspects including: 


  • Review of completed works and current site progress

  • Detailed discussion of structural and technical specifications

  • Alignment on the master project schedule and upcoming milestones

  • Identification of potential risks and mitigation measures

  • Coordination of procurement and resource allocation


The meeting was productive and resulted in clear action points to ensure continued smooth execution of the project. 


From a quality and safety perspective, construction activities are being carried out in agreement with permitted standards and best practices. Consistent supervision, material checks, and workmanship checks are being conducted to maintain quality control. Safety measures have also been reinforced on-site to ensure a secure working environment for all personnel. 


Overall, the project is progressing satisfactorily, with works progressing as strategic and no major interruptions encountered at this stage. Continued focus will be placed on maintaining momentum, ensuring timely delivery of materials, and achieving upcoming structural milestones.



Photos showing the progress






The Bilal Muslim Mission of Tanzania is calling upon the generous donors to contribute towards this Project.  Funds can be sent through the following channels: 



We are grateful to all the donors for their continued support towards Tabligh projects. We pray that the project progresses well and completes on time.



Secretariat

Housing Development Board


22nd April 2026